- 08:30
- Plenary Lecture
- One West, Wilson Hall
- 08:30 - 09:30
- 09:30
- Equipment Set-up
- Install Pb-Glass counter, two TOF's, and wire chamber onto beamline
- Align equipment using lasers
- Cabeling of Pb-Glass, Scintillation Counters (2 quads), Wire chambers
- Gas connection to wire chambers
- Operational test of the installed counters
- MT6.2, FTBF
- 09:45 - 11:00
- 11:00 Search & Secure of Beam Enclosures
- 10:30
- Beam Program
- Elect Shift Leader
- Set-up Elog
- Request Beam
- Begin Measurments
- Contact MCR to diable beam, during lunch break
- MTest Control Room Room, FTBF
- 11:00 - 12:15
- 11:30
- 12:30
- Lunch
- Students are 'on their own' for lunch.
- Cafeteria, Wilson Hall
- 12:30 - 13:20
- 13:30
- Beam Program
- Request Beam, coordinate program with other Test Beam Users
- Establish trigger logic feeding into TDC, ADC, with trigger holdoff
- Controlled Access, as time permits, for rotation of Pb-Glass block to 30/60/90 degrees to measure various light yield depending on incident angle
- Shift summary into Elog
- MTest Control Room, FTBF
- 13:30 - 17:45
- 14:30
- 15:30
- 16:30
- 17:30
- Clean-Up
- MT6.2, FTBF
- 17:45 - 18:00
- 18:30